Bring-up checklist

The terse working form, revision 3, 12 steps. This is the version printed and stuck to the bench; the method page carries the why at length. Steps are in order and the order matters: cold before hot, passive before active.

RULE 1  Never raise the limit to make it work.
RULE 2  Write the number down before you change anything.
#stepwatching for
1Inspection under magnificationbridges, tombstones, wrong orientation, debris
2Cold resistance, every rail to groundsupply disconnected; under ~100 Ohm is a short, stop
3First power, current-limited, minimum populationlimit ~2x expected idle; modules and cables off
4Rail order and timing on the scopeall channels at once; check which rail may lead which
5Clock presence at the pin that consumes itfrequency, amplitude, shape at the destination
6Reset behaviourrelease timing, bounce, brown-out retrigger
7Strap verification, pin by pinboot-mode pins against the schematic; moved up 2026-08-20
8Loader, then the consoleno characters vs garbled characters are different diagnoses
9Thermal pass in the enclosureto the claimed maximum, sensor on the most sensitive part
10Peripheral walk, one at a timeexercise each alone, note the current draw
11Soak, unattended, in the enclosureminimum 24 h; free air does not count
12Write-up before the bench is clearedtables filled, dashes where unmeasured, outstanding stated

A step with a dash in its result column was not reached, not passed; the checklist is also the record. The same list is in checklist.json if you want to print your own.